Svenska kraftnät Uppsala package: 400 kV lines (Dalekovod)
Grid contractor Dalekovod has won the whole Uppsala package: ten projects for new 400 kV lines between Mehedeby (Tierp) and Odensala (Sigtuna). The contract covers ground and civil works, pylon erection, demolition of existing lines and stringing; construction is planned to start in early 2027, with lines entering service in stages 2028–2032.